Page 45 - LH_Research_Report_2020_Eng
P. 45

7
                75% of public housing units experienced delays in the past five years5% of public housing units experienced delays in the past five years


                 (Figure 22) Number of public housing units that have experienced delays


                    25,000                                                                                    Delay represents
                                                                                                                   75%
                                                                                                              of public housing
                    20,000
                  Number of units  15,000                                                     (85%)          the past five years
                                                                                                                  units in



                    10,000
                                 (88%)                                    (92%)               23,107
                                 14,224               (75%)
                     5,000                            11,146              12,259                                   (36%)
                                                                                                                  6,829
                        0
                                 2015/16             2016/17             2017/18              2018/19             2019/20
                                                                    Year of completion
                 Note: The bracketed percentage are percentages of units delayed out of the total public housing units completed in that year.
                 Sources: Hong Kong Housing Authority, Legislative Council, and Our Hong Kong Foundation
                 By comparing the time lapse between the planned completion and actual completion of public housing projects, we have
                 observed that delays have been common. 75% of public housing units that were completed in the past five years had experienced
                 delays for at least one year.