Rezoning will continue to be the major land source, which will ezoning will continue to be the major land source, which will
                R
                c
                cause more delays in public housing completionsause more delays in public housing completions


                 (Figure 24) Completion of public housing units by land sources, 2020/21–2023/24


                  Rezoning    Redevelopment    New Town / NDA    Others




                                             9%
                                    19%



                                12%


                                              61%







                 Note: The individual figures combined may not add up to the total due to rounding.
                 Sources: Hong Kong Housing Authority, Town Planning Board, Legislative Council, and various newspapers

                 For the upcoming four years, about 61% of public housing units that are to be completed come from rezoned sites.

                    As rezoning process has been unpredictable and delays had occurred in the past, it is expected that
                    more delays in public housing completions will take place.