Case study on delay in public housing projects: the junction of  ase study on delay in public housing projects: the junction of
                    C
                    S
                    Sung Wong Toi Road and To Kwa Wan Road, Ma Tau Kokung Wong Toi Road and To Kwa Wan Road, Ma Tau Kok


                    (Figure 26) The development timeline of the junction of Sung Wong Toi Road and To Kwa Wan Road, Mau Tau Kok


                                         The junction of Sung Wong Toi Road and To Kwa Road, Ma Tau Kok


                        The Government stated its intention to rezone the site out from a larger
                                    CDA site to a standalone public housing site             Sep 2014

                      OZP was approved by the Chief Executive-in-Council (CEinC) and the rezoning   Apr 2016
                                                was completed                                                       If the site was
                                                                                                                      developed
                                                                                                                    immediately...
                              Could the site be developed earlier if the portion of animal management centre was
                           excluded at the time of rezoning or if the schedule of land clearance be managed better?


                                                 Current status
                          Lok Sin Tong applied for short-term tenancy for transitional housing projects   Jul 2019
                                                                                                                    Public housing
                                                                                                                      (600 units)
                                                  Transitional housing                                                2021–2023 [1]
                                                 (100 units if successful)                     2021


                    Note: [1] Assuming that five to seven years are needed for relocation, site formation and engineering works.
                    Sources: District Council, Civil Engineering and Development Department, Town Planning Board, Lok Sin Tong Benevolent Society, and Our Hong Kong Foundation