(Figure 36) Aerial shot of Pik Wan Road sites, Yau Tong
During 2015–2016, CEDD conducted
feasibility studies for the supporting
infrastructure for the site and concluded that
the sites were technically feasible. In 2017,
Site B CEDD started the site investigation and
design for supporting infrastructure for the
site. The studies are still ongoing at present.
Site A
Two doubts were raised after assessing the timeline. First, it was questionable why site A was not developed
earlier. As site A was already rezoned to residential use before 2011, it is inferable that the rezoning application
of site B was the primary consideration. As the public housing shortage was becoming severe, it is logical to
deduce that site A should have been developed as the sites were not geographically linked together. The case
articulated the complexity between balancing the need of comprehensive planning and housing production.