(Figure 36) Aerial shot of Pik Wan Road sites, Yau Tong

                                                                                            During 2015–2016, CEDD conducted
                                                                                            feasibility studies for the supporting
                                                                                            infrastructure for the site and concluded that
                                                                                            the sites were technically feasible. In 2017,
                             Site B                                                         CEDD started the site investigation and
                                                                                            design for supporting infrastructure for the
                                                                                            site. The studies are still ongoing at present.










                                                      Site A









                       Two doubts were raised after assessing the timeline. First, it was questionable why site A was not developed
                       earlier. As site A was already rezoned to residential use before 2011, it is inferable that the rezoning application
                       of site B was the primary consideration. As the public housing shortage was becoming severe, it is logical to
                       deduce that site A should have been developed as the sites were not geographically linked together. The case
                       articulated the complexity between balancing the need of comprehensive planning and housing production.